Capital Projects 
 

Belle Isle Renovation/Addition – Drywall work is 80% complete. Rooftop packaged HVAC units are installed and ONG is finishing gas installation. The units should be working soon. They are currently projecting construction completion by the end of January 2022. We will begin internal meetings November 3, 2021, to discuss the reopening schedule and logistics for reopening of the renovated library.

 

Operations Minutes - September 07, 2021

MLS Operations Update – September 7, 2021

 

Capital Projects 
 

Belle Isle Renovation/Addition – The steel support structure is nearly complete. The framing for the curtain wall (glass store front facing NW Expressway) is installed and the shape of the front of the building is evident. They are currently projecting construction completion by the end of December 2021.

 

Operations Minutes - August 03, 2021

Capital Projects 
 

Belle Isle Renovation/Addition – Steel support structure is nearly complete. The framing for the curtain wall (glass store front facing NW Expressway) is installed and the shape of the front of the building is evident. They are currently projecting construction completion by the end of December 2021.

 

Operations Minutes - July 14, 2021

Capital Projects 
 

Belle Isle Renovation/Addition – Steel support structure is being built but has been delayed by steel acquisition and some rework of architectural drawings. They are currently projecting construction completion by the end of December 2021.

 

New Almonte Library – We are working with the architects on revisions to the preliminary building program/space planning requirements. We anticipate there will be a preliminary report available by late August/early September 2021.

Operations Minutes - June 01, 2021

Capital Projects 
 

Belle Isle Renovation/Addition – Steel support structure is being built but has been delayed by steel acquisition and some rework of architectural drawings. They are currently projecting construction completion by the end of December 2021.

 

New Almonte Library – We are working with the architects on revisions to the preliminary building program/space planning requirements.

 