Construction Updates - March 19, 2014

  • ALMONTE
    • You may recall that there has been some discussion about “building” a permanent Almonte library.  OKC has suggested that MLS provide a “best guess” about the anticipated needs.
  • BELLE ISLE - no update
  • BETHANY - no update
  • CAPITOL HILL
    • A date (4/23) has been set for MLS to formally present our request for additional funding for CH.
    • If approved, OKC and MLS will need to update the Building Program, the Project Agreement and the A/E contract.  After this is completed, the design work can start in earnest.
    • While schedules are a guess at best and an act of arrogance at worst, they are needed to outline responsibilities, define the sequence of activities and to create a road map.  Once the design work is started, the process become a little more predictable.  And while much will change, the following target date have been discussed - MLS Moves Out – April 2015
    • If the move-out date holds, MLS will need to begin the planning process for this work sometime this summer.
  • CHOCTAW - no update
  • DEL CITY - no update
  • DOWNTOWN
    • MLS met with OKC on 3/18 to review the 95% plans for the 180 project.  This project will make significant changes our “front door”.  These will include changes to the landscaping, sidewalk pattern and lighting.
    • This work to be bid latter this spring and construction in front of the library is planned for the spring of 2015.
    • To see a partial copy of the current hardscape plan below (click image or here to see enlarged plan).
  •  EDMOND PARKING
    • MLS issued our comments regarding Edmond’s draft Parking Agreement on 3/6.  While we did not get this finalized in time to present to the Commission in March, we are optimistic that we can do so in April.
  • EDMOND 2 - no update
  • HARRAH - no update
  • JONES
    • The Design Development plans, which represent the 2nd 1/3 of the design process, are expected March 24th.
    • The 1st FF& E (Furniture, Fixture & Equipment) meeting has been scheduled for April 23rd. 
  • MIDWEST CITY - no update
  • NICOMA PARK - no update
  • NORTHWEST
    • OKC officially accepted the Northwest library on February 25, 2014.  In conversation with OKC, this also the start date for the one year warranty. If you have any issues – please contact the CON office.
    • MLS continues to work with OKC on outstanding Warranty issues.
    • Other projects include work on the bollards, drainage channel, the monumental sign and shades on the west windows.
  • RALPH ELLISON- no update
  • SOUTHERN OAKS- no update
  • VILLAGE- no update
  • WARR ACRES- no update
  • WRIGHT- no update