Construction Updates - May 28, 2014
ALMONTE
- MLS continues to work with OKC to create a “best guess” about the anticipated needs for the future Almonte Library.
- On May 15th, J&B Graphics installed evacuation signage at Almonte.
CAPITOL HILL
- We continue to work to get the architectural design team started. To do that, the following items are needed:
- Adjustment to the Space Needs Summary and a Final Programming Rreport.
- MLS issued a final needs document on May 9th to the City of OKC.
- The budget and abatement work has been set at $4,160,000
- We are awaiting Guernsey’s revised report.
- Update & approve the OKC / MLS CH Project Agreement Amendment
- This was approved by the MLC on May 15th
- It is expected to go to City Council on June 10th
- Negotiations & approval of Guernsey Architects Contract Revisions
- The City of OKC & MLS met on May 1st, May 3rd and May 19th to discuss adjustments to the design contract.
- Guernsey is working on a response which should be submitted to OKC for approval in June.
- Issue an updated schedule
- SIGNIFICANT UPDATE – MLS will not need to move out until AFTER summer reading 2015.
- With the completion of the above, we hope the design work can get started by late June.
DOWNTOWN
- MLS is working on a formal request for the funding for the Downtown Library wall panel repairs and the skylight replacement.
- Project 180 – Park Avenue work bids on June 10th. The work on Park Avenue is scheduled for spring, next year.
EDMOND PARKING
- We expect to present a Project Agreement for this work to the Commission in June.
EDMOND 2
- On May 20th, the Edmond held a Capital Project Task Force meeting, which was attended by MLS. In the meeting, Edmond detailed dollar amounts for various capital projects (i.e. Fire Stations, Parks & Recreation, etc). The second Edmond Library was shown to have $6.5 million budget which is far below the $11 million projected by MLS. There remains a lot of work for MLS, Edmond staff, the Edmond community to make this a reality.
JONES
- We are expecting Studio to issue updated DD plans and an estimate this week.
NORTHWEST
- It is anticipated Atlas will begin warranty work in the next 2 weeks. The major work includes the replacement of broken glass, parking lot repairs, and repairs to the outside fire sprinkler system.
- At the City of OKC’s request, they will meet with Construction today (May 28th) to review the next step regarding repairs to the derrick glazing system.
- On May 22nd, HSE Architects and Marsh Engineering submitted a proposal to address the sound issues in the study rooms. Unfortunately, the cost was too high. On to the next plan.
- SRB Engineering has been released to review the issues at the drainage channel.
RALPH ELLISON
- On May 15th, J&B Graphics installed evacuation signage at Ralph Ellison.
SERVICE CENTER
- On May 15th, J&B Graphics installed evacuation signage and a dedication plaque at the Service Center.
SOUTHERN OAKS
- On May 15th, J&B Graphics installed evacuation signage and a masonry award plaque from the original SO construction.