Construction Updates - January 22, 2014
- CAPITOL HILL
- OKC & MLS continues to make progress on securing additional funding for the project. Part of this process includes updating; Guernsey’s Programming Report; the MLS Project agreement; the A&E contract and the Project Schedule. I believe that the design work will begin in March.
- DEL CITY
- Demolition of the bowling alley is scheduled to begin this month.
- The 1st MLS Design Team meeting was held on Thursday, 1/9. We met to review the early program requirements which where developed in late 2011/12. Planning and Materials Selection are currently reviewing the collection needs. Our next meeting is scheduled for 2/7/14.
- EDMOND PARKING
- Edmond and MLS met with Jim Davis 1/17 to review the current “design” progress. Jim presented plans which; add 16 parking spaces, closes access to the alley and adds 10 parking spaces on 1st St.
- The 95% concept plans are due on 1/24 and the final plans and the probable cost estimate are due February 14th.
- At present, it is expected that this information will be presented to the Commission in March.
- If all is approved, the design work could start shortly thereafter and construction could start in August.
- JONES
- An updated elevation of the Jones Library was approved by Jones and MLS on 1/17. The Design Development plans (phase 3 of the 4 step design process) are expect early March.
- NORTHWEST
- Final training for NW Staff was held on January 8th and they have been given the keys. A few punch list item of work remain and project close out documentation is still needed.
- The installation of the additional lights in the Children’s Program Room has been re-scheduled for the week of February 17th.
- A draft Bollard Replacement Plan was submitted to OKC on 1/15 for comments.
- OKC & MLS continues to work on outstanding Warranty issues.